Previous page | Contents | Next page
6.3  |  Military equipment (pre-conflict)
411.  The UOR update for Lord Bach on 7 March highlighted:
176 business cases for equipment capability UORs had been approved at a cost
of “some £488m”.
The list of UORs for the post-conflict phase, Phase IV, continued to be “urgently
developed in parallel with the ongoing work” to develop more detailed planning
guidance and CONOPS. It was likely to focus on potential shortfalls relating
to force protection, infrastructure requirements and Intelligence, Surveillance,
Target Acquisition and Reconnaissance (ISTAR).
Agreement was being sought from the Treasury to increase the total UOR
funding for Phase III by a further £60m. The funding for Phase IV had been
discussed at official level.200
412.  The update stated that the Integrated Project Team (IPT)201 was “actively
assessing” another source to assist in the production of desert pattern NBC suits.
There was a requirement for 94,000 suits, but the contracted supplier could only produce
1,000 a week from the beginning of April (when the cloth to make the suits became
available), and 4,000 plus a week by mid-June.
413.  The DLO had issued sufficient ComboPens for the number of personnel deployed
but “the precise location in theatre of approximately 4,000 [wa]s unconfirmed”. Stocks
had been withdrawn from UK-based warships to mitigate the risk. There would be
sufficient water bottle tops to satisfy all demands by 10 March “and leave a reserve”.
414.  Two UOR sets of sand filters for Lynx helicopters would be delivered by 21 March
with a further three refurbished sets. Further spares would be available from 31 March
and the supplier was producing an additional four sets “at risk” which would be available
from mid-April at a rate of one every two weeks. The MOD was not yet committed to a
contract for these sets but the requirement was likely to be a “high priority” for Phase IV.
415.  At a Chiefs of Staff meeting on 10 March, Lt Gen Reith reported that:
“A full check of in-theatre NBC equipment and redistribution had been completed,
but respirator fitting had been slower than anticipated and was now expected to
complete on 18 Mar.”202
416.  The record of Lord Bach’s meeting on 10 March stated:
“CBRN was in a better position than thought last week … by 17 March all personnel
would have their optimum fit of respirator. The testing was the most advanced in the
world – all personnel had successfully been through the CS gas chamber in their
respirator – we were now providing better still protection. The Commander in theatre
200  Minute CM(SD) to PS/Minister(DP), 7 March 2003, ‘Iraq: Op TELIC UORs’.
201  Teams focused on delivering individual equipment programmes and projects. Their role is explained
further in Section 14.1.
202  Minutes, 10 March 2003, Chiefs of Staff meeting.
65
Previous page | Contents | Next page