Previous page | Contents | Next page
6.3  |  Military equipment (pre-conflict)
384.  The update also stated:
Further to ACM Bagnall’s note earlier that day, PJHQ had set up a
“comprehensive system to review, prioritise and then move UOR equipment into
theatre” once delivery dates were known by industry.
New respirator testing procedures had been introduced to ensure that deployed
personnel would “be adequately protected” after trials found that a proportion of
respirators did not fit properly.
There was a shortfall of 15,000 ComboPens out of a total requirement for
135,000, but “every effort” was being made to procure more and “re-life existing
stock”.
1,000 additional Challenger 2 filters were being procured to support predicted
operation activity.
A plan had been produced for the installation of Combat ID equipment into
selected vehicles.
The 96 fully modified battlefield ambulances were expected to be available
for shipping by “13/14 March”. There were currently only 24 air conditioned
ambulances in theatre.
The delivery of desert clothing, including ECBA covers, was progressing well.
385.  By the end of February, there were “significant” and “severe” shortfalls in
parts of the UK’s NBC protective capability.
386.  The Chiefs of Staff were told that that reflected the compressed timescales
for planning.
387.  The Chiefs of Staff received an update on access to CBRN equipment and NBC
protection on 28 February.190 The paper reported “significant” and “severe” shortfalls in
a number of NBC areas including the availability of Nerve Agent Immobilised Enzyme
Alarm Detectors (NAIAD), Residual Vapour Detectors (RVD) and NBC water bottle tops.
There was, however, a “marked improvement” in ComboPen availability.
388.  The paper stated:
“The compressed timescales available to procure UORs necessarily introduced risk
in achieving earliest possible delivery of all equipments … some shortfalls are now
being exposed.”
389.  Lord Bach received the latest equipment update on the same day, reporting that
173 equipment UORs (totalling “some £487m”) and £320m of operational sustainability
requirements had been approved.191
190  Minute DJW/NBC1 to COSSEC, 28 February 2003, ‘Iraq Contingency Planning – Equipment Issues’.
191  Minute DCDS(EC) to PS/Minister(DP), 28 February 2003, ‘Iraq: Op TELIC UORs’.
61
Previous page | Contents | Next page