14.1 |
Military equipment (post-conflict)
1074.
Gen Granville‑Chapman
responded on 7 September.567
He wrote that
it was
worth
recognising that the UK was operating above concurrency levels
“(which did
not
envisage two medium scale enduring operations over extended LOCs
[Lines of
Communication]
and did not plan for a helicopter fleet to match)”. He also stated
that
the MOD had
“postponed rectifying the acknowledged 15‑20 percent helicopter
shortfall
until at
least 2010” when it had taken £1.5bn of savings against the Future
Rotorcraft
Capability
(FRC) programme in 2004.
1075.
Gen Granville‑Chapman
wrote that Lt Gen Houghton’s “current
battlefield
helicopter
requirements in Iraq and Afghanistan” were being met by the
deployment
of additional
aircraft and the resourcing of additional flying hours in both
theatres.
That increased
level of activity was, “on the face of it, sustainable” and the
requirement
had been
confirmed by the recent Force Level Review.
1076.
In Iraq, there
was little potential for reducing the “aviation bill” in the short
term.
1077.
The nature of
both campaigns required a “critical theatre entry standard”
to
be imposed,
principally the fitting of DAS and long‑range secure
communications.
That meant,
even with UORs to date, 65 percent of the battlefield helicopter
fleet was
“not
deployable”. Planned UORs would reduce that figure to 40
percent.
1078.
Gen Granville‑Chapman
stated that flying hours were limited by the
availability
of trained
crews as much as airframes. The demand was being met by
“redistributing
airframes
and sweating the assets to the maximum degree” but, he
warned:
“There is
not likely to be any let‑up in BH tempo for at least the next five
years which
leaves us
with virtually no capacity to meet increased or new demands and a
real
‘harmony’
problem for our BH people.”
1079.
Four options
to add capability were considered:
•
Leasing –
an option with “limited mileage” because the resolution of
indemnity
and
financing issues, coupled with delivery timescales meant that
significant
new
deployable capability would take at least a year but more likely
three.
Leased
civilian helicopters in the UK could be used for training but would
not
generate
competent crews for operations.
•
Contracting
– using contractor aircraft flown by civilians was an option but
the
aircraft
were not “DAS’d to our standards”.
•
Further
developments to the existing fleet – Puma was scheduled to go out
of
service in
2010 and Sea King Mk4 in 2012. To keep both models going
beyond
those dates
would cost £155m. Options were being considered to make
some
Merlin Mk1s
“dual capable as BH” and to make other aircraft into “a basic
SH”.
567
Minute VCDS
to SofS, 7 September 2006, ‘Helicopter Capability’.
183