77.  Sir Nicholas Macpherson told the Inquiry:
“I don’t think at a macro level this intervention [Iraq] has had a significant effect
on spending elsewhere … I think the peak year of spending was 2003/04, which
was about £1.6bn. When you [the Government] are spending £500bn, £1.6bn is
significant and it bears a lot of attention and focus, but it is not going to divert fiscal
policy in a massive sense.”63
78.  Mr Brown told the Inquiry:
“I think we managed to meet the requirements of Iraq and Afghanistan without
having to cut other services …
“… it did make my life more difficult, because we had to find £17bn over a period of
time, but we thought and believed that these [costs] were manageable, given the
priority that we attached to doing the things that we did.”64
79.  The £17bn referred to by Mr Brown represented the NACMO in Iraq and
Afghanistan.
80.  Mr Boateng told the Inquiry that the Treasury’s analyses of the impact of war on
the UK’s public finances were not conducted with the intention of “second‑guessing”
Ministers, but to enable the Treasury to contribute to planning and policy discussions.65
81.  The Treasury provided a more detailed analysis on the potential impact of
intervention in Iraq on UK public finances for Mr Brown on 22 October.
Agreement on arrangements for funding Urgent Operational
Requirements
82.  Section 6.3 describes the increasing concern within the MOD over possible delays
in procuring and delivering UORs for operations against Iraq arising from the decision in
July not to engage the Treasury in military contingency planning.
83.  On 19 September, in the context of discussions within the MOD on how to secure
funding for a number of critical UORs relating to potential UK Special Forces operations
in Iraq, the Private Office of Sir Kevin Tebbit, MOD Permanent Under Secretary, advised
that Sir Kevin believed that Mr Hoon should discuss the issue of funding for UORs
with Mr Brown “as soon as possible”, which would be at their meeting scheduled for
23 September.66
63 Public hearing, 22 January 2010, page 9.
64 Public hearing, 5 March 2010, pages 103–105.
65 Public hearing, 14 July 2010, page 22.
66 Minute APS/PUS [MOD] to Sec(HSF)2, 19 September 2002, ‘Op ROW: SF Urgent Operational
Requirements (UORs)’.
458