Previous page | Contents | Next page
The Report of the Iraq Inquiry
262.  The Chiefs of Staff had also considered a “CBRN Risk Paper” on 6 November
and the key equipment issues arising were covered in Lt Gen Pigott’s UOR update on
18 November.128 The time needed to procure additional COLPRO under UOR action
was “directly related to the amount of equipment required” and it was possible that the
quantity which could be procured and fielded against “the most demanding timeframe
may be insufficient to meet the full requirement”. That could have an impact upon the
UK’s concept of operations (CONOPS). Options would be presented to the Chiefs of
Staff “once the extent of the likely shortfall” was confirmed.
263.  Lt Gen Pigott reported that 20 UORs had been approved to date, and a further
137 USURs endorsed. The latest ISD being used to gauge the delivery of UORs was
the end of February for Packages 1 and 2 and the end of March for Package 3.
264.  There were some key equipment gaps “that may not be fully addressed by the
UOR process and for which Chiefs of Staff’s direction on prioritisation and risk may be
required”, including:
ECBA – “ … it is possible we may not be able to procure sufficient numbers
within the timeframe; this may necessitate differential levels of force protection”.
Desert clothing and boots – “It is likely that the numbers required will exceed
the UK’s manufacturing capability. There are operational, force health and
presentational implications in not providing troops with appropriate clothing.”
265.  Options would be presented to the Chiefs of Staff once procurement timelines had
been confirmed with industry.
266.  Maj Gen Fry advised Adm Boyce on 22 November that it would take some four
months from the order to deploy for the northern option (whether Package 2 or 3), and
more than five months for the southern option.129
267.  A DCRS official informed Mr Hoon on 22 November that contracts were shortly to
be let for clothing, combat boots and body armour, and the procurement of these items
would be highly visible.130 The official wrote that the “continuing uncertainty over the size
of the operation” meant that, initially, the procurement figures would be:
clothing for 15,000 personnel;
20,000 pairs of desert boots; and
50,000 body armour plates.
128  Minute DCDS(C) to COS, 18 November 2002, ‘Iraq Contingency Planning – Urgent Operational
Requirements and Related Issues’.
129  Minute DCJO(Ops) to PSO/CDS, 22 November 2002, ‘Potential Operations in Iraq – Northern and
Southern Timelines’.
130  Report DCRS 1 to APS/SofS [MOD], 22 November 2002, ‘Potential Operations in Iraq: Letting of
Contracts for Combat Clothing/Body Armour’.
40
Previous page | Contents | Next page